This project model will demonstrate the completion of a project that contains three separate tasks, all modeled with the same structure. proj1.mdl models only one task. This model will be saved as proj2.mdl and modified to take subscripts representing the three tasks.
EITHER
Ø | Open the model proj1.mdl contained in the directory UserGuide\chap17 (the Complete directory contains finished versions for reference). |
OR
Ø | Sketch the model structure and enter the equations as shown on the next page (INITIAL TIME = 0, FINAL TIME = 100, TIME STEP = 0.125, Units for Time: Month). |