max work accomplishment=8

Units: Drawing/Month

task is active=
IF THEN ELSE( Work Done < task size, 1, 0)

Units: Dmnl

task size=180

Units: Drawing

work accomplishment=
max work accomplishment * task is active

Units: Drawing/Month

Work Done = INTEG(
work accomplishment,
       0)

Units: Drawing

Work To Do = INTEG(
- work accomplishment,
       task size)

Units: Drawing

 

ØMark Work To Do as a Supplementary variable in the Equation Editor.
ØIf you like, make a simulation run to examine the behavior of the model.  You will find that Work Done (a single task) increases linearly from zero to a final value, then stays constant.
ØSelect menu File>Save As… and type in the name proj2.